Cruce - Del SolTransmission Improvements Project


[Español]

Following Texas' winter storms in February 2021, the Public Utility Commission of Texas (PUC) and Electric Reliability Council of Texas (ERCOT) identified the need for additional transmission lines in the Rio Grande Valley.

As part of the larger RGV Transmission Improvements Project, AEP Texas, ETT and South Texas Electric Cooperative (STEC) representatives are partnering to engineer and construct the Cruce – Del Sol Transmission Improvements Project to strengthen the electric grid and help withstand weather impacts.

The Cruce - Del Sol Transmission Improvements Project involves building AEP Texas' future Cruce Substation, located southeast of Hebbronville, and approximately 55 miles of double-circuit 345-kilovolt (kV) transmission line from ETT'S Del Sol Substation, located near Rio Grande City, to the future Cruce Substation.

The Cruce to Del Sol Transmission Improvements Project will improve regional reliability and resiliency by:

  • Helping strengthen the power grid against severe weather events.
  • Reducing the likelihood and duration of wide, community-sustained outages.
  • Providing additional capacity for growth and economic development.

Company representatives will reference public input to make necessary adjustments to the potential route links. The PUC will review the preliminary route links and consider public feedback before identifying a final route for the Cruce - Del Sol Transmission Improvements Project. Company representatives accepted comments on the potential route links through January 6, 2023, with multiple opportunities for in-person open houses in December 2022. Feedback was also accepted through the website feedback form, email, phone and mail.

Project Updates

Public open houses were hosted in December 2022 in which project team members were available to review maps and answer any questions. 

Regulatory Updates

June 2023: Company representatives filed a Certificate of Convenience and Necessity (CCN) with the Public Utility Commission of Texas (PUC) following a review of public input on route link development and additional route analysis on June 30, 2023.

February 2024: The PUC approved the project and line route on February 1, 2024. View the PUC final order here.

Project Releases

Timeline

Project Timeline

Structures

Structure

The typical structure characteristics planned are:

  • Typical Height: 140 feet*
  • Typical Distance Between Structures:
    Monopole: Approximately 800-1,000 feet*
    Lattice: Approximately 1,200-1,400 feet*
  • Typical Right-of-Way Width: 150 feet*

*Representative structure, exact height and right-of-way requirements may vary based on geography and other factors.

The current route links run through Brooks, Duval, Jim Hogg and Starr counties in Texas. Multiple potential route links will be presented to determine the final proposed routes prior to CCN filing. The companies will not build all route links; rather, they will provide multiple route options for the PUC to identify the final route. This could include a combination of the proposed route links that connect from the Cruce Substation to the Del Sol Substation.

AEP Texas, ETT and STEC implement a comprehensive siting process that strikes a balance between building infrastructure and respecting land use and the environment. All companies incorporate and review public input along with the following factors:

  • Existing land use
  • Public lands: state, federal, and military lands
  • Conservation lands and local parks
  • Sensitive species and habitats
  • Soils and topography
  • Historic and cultural resources
  • Existing infrastructure

Similar to other linear infrastructure projects, right-of-way representatives from AEP Texas, ETT and STEC work directly with landowners to obtain the necessary land rights for the project once the PUC determines the final route.

Right-of-way agents work with landowners on the details of easements to reduce impacts on farming practices and personal land use. There also can be compensation for crop loss or damages during construction, which will be handled during one-on-one discussions with involved landowners.

Landowners and the environment will be treated with respect in constructing the new line. Property owners will be treated fairly and made whole for property encumbered by the transmission line project.

We prioritize:

  • Proactive and early engagement with landowners and stakeholders
  • Transparent proceedings throughout the project
  • Maintaining a positive working relationship with all regulatory and environmental agencies

Project Maps

Please note that these maps are preliminary and do not reflect any final power line route decisions.

OVERVIEW MAP

Step 1: Below is an Overview Map that displays the entire project area. Please use the Overview Map to find the general location of your property.

Resources

RGV Transmission Improvements Project Property Easements Project Fact Sheet Access Roads Field Activities Logo of AEP Texas, Electric Transmission Texas, and STEC

AEP Texas serves over one million consumers in the deregulated Texas retail electric marketplace.

www.AEPTexas.com

www.ETTexas.com

www.STEC.org

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.