translate-globe-icon

WheelersburgArea Improvements Project


AEP Ohio representatives plan to upgrade the electric transmission network serving customers in Scioto County.

The Wheelersburg Area Improvements project involves:

  • Building about 5 miles of 138-kilovolt (kV) power line
  • Rebuilding about 2 miles of 138-kV power line
  • Removing about 10 miles of transmission facilities
  • Installing two switch poles to control the direction of electricity flow throughout the lines
  • Replacing Wheelersburg Substation located on Earwood Lane with Sweetgum Substation located near OH-522 and Mill Road
  • Building Althea Substation located off Gallia Pike in Franklin Furnace

The project provides an additional power source to the area and enhances electric service reliability to customers. The additional power source allows crews to retire about 10 miles of deteriorating power line that dates back to 116. Company representatives plan to build Sweetgum Substation to replace the aging Wheelersburg Substation to allow for adequate space for the modern equipment needed to continue serving area customers. Adding switch poles to the area provides the ability to isolate equipment from the power grid, speeding recovery of service when an outage occurs.

Company representatives plan to evaluate study segments in the area. Study segments are multiple alternatives presented to determine a line route. Company representatives do not build all study segments, rather, they select one route to build based on public feedback and feasibility.

This project requires Ohio Power Siting Board (OPSB) approval.

Project Updates

Summer 2023:The Ohio Power and Siting Board has announced the dates for the public hearing and the adjudicatory hearing.

The local public hearing will be held at 5 p.m. Tuesday, August 8, 2023, at the Wheelersburg Middle School, 800 Pirate Drive Wheelersburg, Ohio 45694.

The adjudicatory hearing will be held at 10 a.m. Thursday, September 7, 2023, at the Public Utility Commission of Ohio - Hearing Room 11-C located at 180 East Broad Street, 11th Floor in Columbus, Ohio 43215.

Company representatives have filed the following segments with the OPSB.

  • Click here for more information on the Cottrell North and South 138-kV Transmission Line Extension Project.
  • Click here for more information on the Althea - Sweetgum 138-kV Transmission Line Project.

Public Notice

Timeline

 
Project Timeline
 

Structures

Structure

The project involves the use of single steel pole and H-frame structures.

Pole Height Range: 75-100 feet
Right-of-Way Width Range: 80-100 feet

*Exact structure, height, and right-of-way requirements may vary

Resources

Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Kia Clay

Project Outreach Specialist
614-933-2998
kclay1@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.