Lott138-kV Transmission Line Project


AEP Ohio representatives plan power grid upgrades in Delaware County. The project involves building about 4 miles of 138-kilovolt transmission line and a substation. These improvements strengthen the local power grid by reducing the likelihood of power outages and speeding recovery of service when outages occur.

Project Updates

Early 2023: Please join us from 5:30 p.m. to 7:30 p.m. on Wednesday, February 1, at Centerburg High School Cafeteria located at 3782 Columbus Road in Centerburg. There is no formal presentation, so you can arrive at any time during the event. You can view detailed maps and talk with team members about the proposed route alternatives.

Please share your input by Friday, February 10.

Project Map

Project Map (PDF)

Project Releases

Lott 138 kV Transmission Line Project Application Part 1 (PDF)
Lott 138 kV Transmission Line Project Application Part 2 (PDF)
Lott 138 kV Transmission Line Project Application Part 3 (PDF)

Timeline

Project Timeline

Structures

Structure

The project involves the use of single, steel poles.

Structure Height: 65-90 feet*
Right-of-Way Width: 80 feet*

*Exact structure, height and right-of-way may vary

Resources

AEP Right-of-Way Process Virtual Open House Project Fact Sheet Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Meghan Blankenship

Project Outreach Specialist
304-784-0556
mdblankenship@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.