St. ClairsvilleArea Improvements


AEP Ohio representatives plan power grid upgrades near St.Clairsville. Upgrades involve constructing about 1 mile of 69-kilovolt (kV) transmission line, rebuilding about 12 miles of 69-kV transmission line and installing equipment to improve the operation of the power grid.

Company representatives plan to rebuild the power line in the existing right-of-way, although they might need to acquire new easements or supplement current easements to ensure the safe construction, operation and maintenance of the line.

Project Updates

Summer 2023: Construction is ongoing and is scheduled to be completed late summer 2024.

Spring 2023: Crews and contractors are currently installing steel poles and wire along the power line route. Upon completion of construction, right-of-way agents plan to work with landowners during restoration.

Timeline

Project Timeline

Structures

Structure

The project involves replacing wooden poles with steel poles.

Structure Height: Approximately 95 feet
Right-of-Way Width: Approximately 60 feet

* Exact structure, height and right-of-way may vary

Resources

Property Easements Project Fact Sheet Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Kia Clay

Project Outreach Specialist
614-933-2998
kclay1@aep.com