Northeast Lima - Columbus GroveTransmission Improvements Project


AEP Ohio representatives plan to upgrade the electric transmission network serving customers in Putnam and Allen counties.

The project involves:

  • Rebuilding about 10 miles of 69-kilovolt (kV) transmission line
  • Building about 1 mile of 69-kV transmission line

The planned improvements involve replacing deteriorating wooden poles from the 1950s with modern steel poles and reduce the need for frequent power line maintenance. Building a new power line provides an additional power source and improves electric reliability in the area. A stronger transmission grid benefits the local distribution companies and cooperatives, such as Midwest Electric Cooperative, who receive power from the transmission lines.

Project Updates

Summer 2023: Company representatives plan to begin construction in fall 2024 and expect completion in summer 2026.

Early 2023: Company representatives announced the final line route for the 1 mile of new power line and evaluated study segments. Right-of-way representatives plan to meet with landowners to discuss their property.

Timeline

 
Project Timeline
 

Structures

Structure

Crews plan to build the line using single steel poles.

Proposed Structure Height: 70 - 100 FEET
Right-of-Way Width: 60 FEET*

*Exact structure, height and right-of-way may vary

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Brian Recker

Project Outreach Specialist
380-205-5381
brecker@aep.com