Northeastern Power Station - Vinita Transmission Line Rebuild Project


Public Service Company of Oklahoma (PSO) representatives plan improve electric reliability northeastern Oklahoma by rebuilding about 46 miles of 138-kilovolt (kV) transmission line in Craig and Rogers Counties. PSO representatives expect to begin construction in Spring 2028 and conclude in Late 2029.

The project involves:

  • Rebuilding approximately 46 miles of 138-kilovolt (kV) transmission line between the Northeastern Power Station in Oologah and the Vinita Junction Substation in Vinita
  • Rebuilding approximately 2.5 miles of 69-kV transmission line between the Vinita and Vinita Junction substations
  • Reconductoring approximately 2.5 miles of transmission line circuit through the Vinita area.

Timeline

*Move slider to view project timeline

Structures

Open project structure modal

Typical Structure Height: Approximately 95 feet*
Typical Right-of-Way Width: Approximately 100 feet*
Typical Distance Between Structures: Approximately 600 feet*

*Exact structure types, height and right-of-way requirements may vary

Resources

Property Easements Project Fact Sheet Project Map Access Roads Field Activities

AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.

www.AEPTexas.com

PSO Outreach Team

Project Outreach Specialist
800-272-4826
pso_outreach@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.