translate-globe-icon

Stuart Area Improvements: Stuart - FloydTransmission Line Rebuild Project


Appalachian Power officials plan to upgrade the local power grid.

The Stuart - Floyd Transmission Line Rebuild involves:

  • Rebuilding approximately 20 miles of 69-kV transmission line to 138-kV
  • Upgrading one substation
  • Expanding one substation

Please review the information on this website to learn more about the project.

Project Updates

08/04/2023 - The project team submitted an application to the Virginia State Corporation Commission, on July 20, 2023. If the SCC approves the project, Appalachian Power representatives will move forward with the project and landowners along the power line route will be contacted to discuss next steps.

To view the application, please visit AppalachianPower.com/Stuart.

6/23/2023 - Appalachian Power representatives are preparing to file the project with the Virginia State Corporation Commission (SCC) to seek approval for the upgrades. Landowners in the project area will be notified via mail once the application is submitted.

9/29/2022 - Appalachian Power representatives have determined a proposed power line route and plan to submit an application to the Virginia State Corporation Commission (SCC) in early 2023 seeking approval for the upgrades. Appalachian Power’s right-of-way team is committed to working with affected landowners throughout the easement acquisition and construction process.

2/9/2022 - Appalachian Power invites community members and landowners in the project area to learn more at a pair of upcoming in-person open houses.

  • Wednesday, February 23 from 5:00 – 7:00 p.m. at Floyd Elementary School, 531 Oak Hill Dr. SW, Floyd, VA 24091
  • Thursday, February 24 from 5:00 – 7:00 p.m. at Stuart Rotary Field (Memorial Building), 420 Woodland Drive Stuart, VA 24171

Project team members plan to wear face coverings at the in-person open houses and encourage those who plan to attend the in-person events to also wear face coverings. For the safety of the community and the project team, those who are experiencing COVID-19 symptoms or are feeling unwell please consider visiting the virtual open house to learn more about the project.

Project Releases

News Release, August 17, 2023 (PDF)

News Release - September 29, 2022 (PDF)

News Release - February 9, 2022 (PDF)

Timeline

Project Timeline

Structures

Structure

Crews plan to rebuild most of the line using steel, H-frame structures; however, crews plan to use steel, double circuit single-pole structures between Highway 221 and the Floyd Substation and north of the proposed Mayo River Substation. At select locations, crews may use steel single-pole structures, lattice towers and three-pole structures with guy wires to meet engineering needs.

Proposed structures will be typically 35 feet taller on average than the existing structures.

Existing Structure Height: Approximately 55 feet*
Typical Structure Height: 80-100 feet*
Right-of-Way Width: Approximately 100 feet*

*Exact structure, height and right-of-way requirements may vary

Project Maps

Resources

Project Fact Sheet Project Map Access Roads Field Activities

Appalachian Power serves approximately 1 million customers in West Virginia, Virginia and Tennessee.

www.AppalachianPower.com

Cortney Mustard

Project Outreach Specialist, Sr.
833-760-0604
APCO_Outreach@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.