Joshua Falls 765-kV Substation Relocation Project


Appalachian Power representatives plan to relocate and upgrade the Joshua Falls 765-kilovolt (kV) Substation in Campbell County. The substation relocation is proposed to accommodate the Valley Link Transmission Project. For more information about the Valley Link project visit the Joshua Falls to Yeat website here: Joshua Falls to Yeat - Valley Link

The project involves:

  • Building approximately 1.5 miles of new 765-kV transmission line
  • Building approximately 2.7 miles of new 138-kV transmission line
  • Relocating and upgrading the Joshua Falls 765-kV Substation
  • Retiring the existing Joshua Falls 765-kV Substation
  • Removing approximately 3 miles of 765-kV transmission line

This project increases electric reliability for area customers, increases substation capacity to meet future needs and improves substation site conditions to avoid steep terrain and grading issues.

Project Updates

June 2026: Appalachian Power representatives announced the Joshua Falls 765-kV Substation Relocation Project. We plan to host an in-person open house in the area to provide an opportunity for area residents to meet and talk with project representatives. Since there is no formal presentation, open house attendees may join the planned event at any time.

Thursday, July 23, from 4:30 p.m. - 7:30 p.m.
Thomas Terrace Baptist Church
10660 Richmond Highway, Lynchburg, VA 24504

Timeline

*Move slider to view project timeline

Structures

Open project structure modal

Crews plan to install steel H-frame and lattice tower structures along the 138-kV route

Typical Structure Height: Approximately 90 - 120 feet*
Typical Right-of-Way Width: Approximately 100 feet*

*Exact structure types, height and right-of-way requirements may vary


Crews plan to install horizontal lattice and delta lattice tower structures along the 765-kV route

Typical Structure Height: Approximately 135 - 165 feet*
Typical Right-of-Way Width: Approximately 200 feet*

*Exact structure types, height and right-of-way requirements may vary

Typical Substation**

Open project substation modal

Substations serve as electrical intersections directing the flow of electricity and either decrease or increase voltage levels for transport. Substations transform 69-kV and 138-kV electricity into lower distribution level voltages such as 34.5-kV, 12-kV, or 7.2-kV.

Typical Substation Height: Approximately 50 feet**

**Substation shown is a general depiction of the proposed facilities for the project. It does not represent final design.

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Appalachian Power serves approximately 1 million customers in West Virginia, Virginia and Tennessee.

www.AppalachianPower.com

Nancy Miller

Project Outreach
833-760-0604
APCO_Outreach@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.