Appalachian Power representatives plan to upgrade the electric transmission grid in Botetourt County. For the Daleville Area Transmission Improvements Project, the project team is evaluating options for:
*For the ~7-mile portion from Mount Union Substation - Cloverdale Substation, the transmission line will primarily be reconductored (same structures, new wire). The remaining ~10 miles of line must be rebuilt due to structure capacity.
The project provides power to a new customer, supports increasing electricity demand, and enhances electric service reliability for customers.
Crews plan to use steel single-pole structures to rebuild the 10 miles of transmission line where the structures need replaced due to capacity.
Existing Structure Height: 55 - 110 feet*
Proposed Structure Height: 50 - 130 feet*
Typical Right-of-Way Width: 80 - 100 feet*
*Exact structure types, height and right-of-way requirements may vary
Appalachian Power serves approximately 1 million customers in West Virginia, Virginia and Tennessee.