AEP Texas representatives plan to upgrade the electrical transmission system in Victoria, Wharton and Jackson counties.
The project involves:
Project benefits include:
AEP Texas officials plan to apply for a Certificate of Convenience and Necessity (CCN) application with the Public Utility Commission of Texas (PUCT) following a review of public input on route link development and additional route analysis. Project representatives expect to file a CCN application by early 2027. The PUCT determines the final route.
August 2026: AEP Texas representatives plan to host two in-person open houses for this project. Please join us at one of our open houses listed below:
Jackson County
September 1, 2026
Harry Hafernick Recreation Center - Auditorium
891 Brackenridge Pkwy
Edna, TX 77957
5 - 7 p.m.
Victoria County
September 2, 2026
Victoria Community Center
2905 E North St.
Victoria, TX 77901
5 - 7 p.m.
During the open houses, landowners can view detailed maps, talk to project team members about project plans, the PUCT regulatory approval process, the project need and benefits and the routing analysis process. There will be no formal presentation, so attendees may arrive at any time.
Typical Structure Height: Approximately 100 feet*
Typical Distance Between Structures: Approximately 800 - 900 feet*
Typical Right-of-Way Width:Approximately 100 feet*
*Exact structure types, height and right-of-way requirements may vary
AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.