North YalePower Connect


PSO officials plan to enhance the local power grid in north Tulsa County. These enhancements support economic development in the area and ensure continued reliable service for area customers.

Project Updates

Late 2024: Company representatives are evaluating route options to build a new 3-mile, 345-kilovolt (kV) power line connecting to a new AEP substation.

Route options are multiple alternatives presented to determine a final line route. Crews do not build all route options, rather, PSO selects one route to build based on public feedback and feasibility.

PSO welcomes you to attend an open house to view detailed maps, talk to team members, learn more about the project and discuss the construction process. The open house takes place 5 - 7 p.m. on January 7, 2025 at Barnes Elementary, 7809 East 76th Street North, Owasso, OK 74005. There is no formal presentation, so you can arrive at any time during the event.

PSO asks that you share your feedback on route options by January 17, 2025.

Timeline

 
Open project timeline modal
 

Structures

Open project structure modal

PSO crews plan to install steel monopole structures

Typical Height: 140 - 160 feet*
Typical Distance Between Structures: 1,000 feet*
Typical Right-of-Way Width: 150 feet*

*Exact structure, height, and right-of-way requirements may vary.

Typical Substation

Open project substation modal

Proposed Substation Footprint: 820 feet by 640 feet

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Public Service Company of Oklahoma serves 538,000 customers in Oklahoma.

www.PSOklahoma.com

Katelyn Hahn

Project Outreach Specialist
918-313-8240
PSO_Outreach@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.