Public Service Company of Oklahoma (PSO) representatives plan to improve the electric transmission system in Carter, Johnston, Coal, Atoka and Pittsburg counties. The Lone Grove - Kiowa Transmission Line Rebuild Project involves rebuilding approximately 88 miles of transmission line in southern and southeastern Oklahoma to increase reliability and strengthen the local power grid. Crews plan to begin construction in fall 2024 and conclude by early 2026.
The Lone Grove - Kiowa Transmission Line Rebuild Project is part of the larger Southern Oklahoma Transmission Improvements Project. To learn more about this project, click HERE.
Fall 2024: PSO crews and contractors have worked since the spring to install temporary gates, fencing and other access along the power line route.
Crews plan to begin construction on the first segment of the line rebuild this fall. The construction sections and timeframes are as follows:
In early 2025, PSO representatives plan for contractor forestry crews to travel along the power line route trimming or removing trees and other woody-stemmed vegetation from PSO's right-of-way. This ensures the electrical grid's reliability for customers while keeping the public and power line crews safe.
Volkert, Inc., continues to serve as PSO’s right-of-way representative for this project. Volkert right-of-way agents are contacting affected landowners to discuss field activities, easement acquisition and construction.
Early 2024: As this project has evolved, the timeline has shifted.
Pre-construction activities along the line route are ongoing, with crews working from east to west.
This work includes:
• Installing temporary gates, fencing and
access roads
• Installing culverts for
water management
PSO representatives plan to start transmission line construction in the fall and conclude by early 2026.
Summer 2023: Volkert, Inc., serves as PSO’s right-of-way representative for this project. Volkert right-of-way agents plan to contact affected landowners to discuss field activities, easement acquisition and construction. PSO representatives expect pre-construction activities to start in early fall 2023. To safely perform these activities, crews may need to:
• Remove woody-stemmed vegetation from the right-of-way
• Install temporary gates, fencing and access
roads
• Install culverts for water
management
Crews plan to start construction activities in fall 2023 and conclude by early 2025.
Late 2022: Volkert, Inc., serves as PSO’s right-of-way representative for this project. Volkert right-of-way agents plan to contact affected landowners to discuss field activities, easement acquisition and construction.
PSO crews plan to install steel single poles on this project.
Typical Structure Height: Approximately 145 feet*
Typical Distance Between Structures: Approximately
800 feet*
Typical Right-of-Way Width: 150 feet
*Exact structure design, height and right-of-way requirements may vary.
Public Service Company of Oklahoma serves 538,000 customers in Oklahoma.
Project Outreach Specialist
918-237-6736
mchames@aep.com
Your message has been sent! We'll be in touch shortly.