AEP Ohio representatives plan power grid upgrades in northern Vinton County. The project involves building just under 2 miles of 138-kilovolt transmission line and a switch to isolate equipment from the power grid. Upgrades improve power grid functionality and operation.
Late 2023: AEP Ohio crews plan to start construction in January and conclude late 2024. Property ROW LLC continues to serve as AEP Ohio’s right-of-way representative on this project. Landowners along the line route can expect to hear from Eric Correll, Lead Right-of-Way Agent on the project.
Summer 2023: The Ohio Power Siting Board (OPSB) recently approved AEP Ohio's project applications (case no. 23-0123-EL-BLM, 23-0122-EL-BNR). AEP Ohio crews expect to begin construction in early 2024 and conclude fall 2024.
Project Map (PDF)
Structure type varies depending on location and engineering design. Company engineers strive to limit the impact of the line on its surroundings while maintaining a buildable design.
Structure Height Range: 60-100 feet
Right-of-Way Width: Approximately 100 feet
* Exact structure, height and right-of-way may vary