Vassell - Green ChapelTransmission Enhancements Project
AEP Ohio officials plan power grid improvements to connect new customers to the electric grid and maintain reliable electricity for customers in Delaware and Licking counties. Customer demand for electricity is anticipated to grow about four times the current need over the next five years. As a result of the area's economic development, the power grid in Delaware and Licking counties must be upgraded.
The project involves building two 13-mile 345-kilovolt power lines connecting Vassell Substation off State Route 37 in Sunbury to two new substations off Green Chapel Road in New Albany
This project requires Ohio Power Siting Board (OPSB) approval.
Updates
Late 2024: AEP Ohio representatives plan to begin access road installation and tree clearing activities along the Vassell-Green Chapel Transmission Line corridor, beginning in January 2025. The activities are only planned to occur where the company has acquired voluntary easements from property owners.
AEP Ohio representatives plan to construct the transmission lines in two phases:
- Phase 1 (Vassell-Green Chapel): Early 2025 – Summer 2026
- Phase 2 (Vassell-Curleys): Fall 2025 – Summer 2027
Following construction, company representatives plan to work with affected property owners on restoration activities.
If you have any questions about construction and the upcoming activities, please reach out to Steve Terlesky with OR Colan at 267-210-6794 or sterlesky@orcolan.com.
Summer 2024: AEP Ohio representatives have filed two Letter of Notifications with the Ohio Power Siting Board (OPSB) for both of the proposed approximately 13-mile 345-kV lines as the Vassell-Green Chapel 345 kV Transmission Line Adjustment Project, Public Utilities Commission of Ohio Case No. 24-0791-EL-BLN, and the Vassell-Curleys 345 kV Transmission Line Adjustement Project, Public Utilities Commission of Ohio Case No. 24-0792-EL-BLN
OR Colan (ORC), AEP Ohio's right-of-way vendor for this project, continue to talk with involved property owners about upcoming field activities and easements. The utility needs to acquire easements for an approximate 150-foot right-of-way corridor. Easements are defined land rights that allow for the safe construction, operation and maintenance of the power lines.
Proposed Schedule
Structures
Company representatives anticipate utilizing AEP's BOLD (Breakthrough in Overhead Line Design) technology, which is capable of operating more efficiently than conventional transmission pole designs.
Structure Height: 150 feet*
Right-of-Way Width: 150 feet*
*Exact structure, height and right-of-way may vary
Project Releases
Vassell-Green Chapel 345 kV Transmission Line Adjustments #2 Project - Application (PDF)
Vassell-Green Chapel 345 kV Transmission Line Adjustments #2 Project - Public Notice (PDF)
Vassell – Green Chapel 345 kV Transmission Line Project Application (PDF)
Vassell – Green Chapel Transmission Line Application - Notice of Adjustment (PDF)
Vassell – Curleys 345 Transmission Line Project Application (PDF)
Vassell – Curleys 345 kV Transmission Line Public Notice (PDF)
Vassell-Green Chapel 345 kV Transmission Line Adjustment Project Application (PDF)
Vassell- Curleys 345 kV Transmission Line Adjustment Project Application (PDF)
Public Notice (PDF)
Resources
Property Easements Fact Sheet Map Access Roads Field ActivitiesAEP Ohio provides electricity to nearly 1.5 million customers.
AEP Ohio Outreach
614-259-8201
Outreach@AEPOhioTransmission.com
Your message has been sent! We'll be in touch shortly.