Millwood - HowardTransmission Line Rebuild Project


AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers between Howard and Shelby in Richland and Knox counties. The Millwood - Howard Transmission Line Project involves rebuilding about 36 miles of power line.

Plans call for rebuilding the power line in the existing right-of-way, although company representatives might need to acquire new easements or supplement current easements to ensure the safe construction, operation and maintenance of the line.

Project Updates

August 2022: Karen Broach of Contract Land Staff, LLC, serves as the right-of-way agent representing AEP Ohio on this project. Landowners can expect to hear from a right-of-way agent in the coming weeks. If you have questions or want to reach out to Karen, you can call (419) 564-1967 or email Karen.Broach@contractlandstaff.com.

Timeline

 
Project Timeline
 

Structures

Structure

This project involves the use of steel single-pole structures.

Structure Height: Approximately 100 feet*
Right-of-Way-Width: Approximately 100 feet*

*Exact structure, height and right-of-way may vary

Resources

Property Easements Project Fact Sheet Project Map Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

AEP Ohio Outreach

614-933-2998
AEPOhio_Outreach@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.