West Lancaster - West MillersportTransmission Line Rebuild Project


AEP Ohio representatives plan to strengthen the transmission system in Fairfield County, addressing the growing power demand in the area and enhancing reliable electric service to area customers.

The West Lancaster - West Millersport Transmission Line Rebuild Project involves:

  • Rebuilding approximately 15 miles of 138-kilovolt transmission line from southwest Lancaster to southwest Millersport.
  • Replacing deteriorating wooden poles with single steel poles.
  • Upgrading the West Lancaster and South Baltimore substations.

*This project requires Ohio Power Siting Board (OPSB) approval.

Project Updates

Fall 2024: Pre-construction activities are underway. Construction is anticipated to begin in early 2025.

Project Releases

Timeline

Project Timeline

Structures

Structure

This project involves the use of steel single pole structures.

Typical Pole Height: Approximately 85 feet*
Typical Right-of-Way Width: Approximately 100 feet*

*Exact structure types, height and right-of-way requirements may vary

Resources

Property Easements Project Fact Sheet Project Map Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Stephanie Eisenberg

WSP representing AEP Ohio
614-259-8201
Outreach@AEPOhioTransmission.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.