LEGEND

    Lamping - Woodsfield Transmission Line Project

    AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers in Monroe County. The Lamping-Woodsfield Transmission Line Project involves building about 10 miles of 69-kilovolt transmission line and upgrading a substation.

    The project involves:

    • Building about 10 miles of power line
    • Upgrading a substation

    Company representatives plan to build the power line in an approximate 60-foot right-of-way corridor and plan to acquire new property easements to ensure the safe construction, operation and maintenance of the line. Crews are expected to begin rebuilding the line at the beginning of 2021 and conclude in the summer of 2023.

    Project Updates

    Summer 2020: At AEP Ohio, we are committed to keeping our customers and employees safe and healthy amid the COVID-19 pandemic. As a result of the social distancing recommendations made by the Centers for Disease Control and Prevention (CDC), we invite you to join us for a virtual open house to learn more about the project and share your input on possible route options for the new power line. Please provide comments through the "Contact Us" link. Please share your input by July 10.

    Fact Sheet

    Map

    Timeline


    Structures

    This project involves the use of steel, H-frame structures.

    • Structure Height: Approximately 70 feet*
    • Right-of-Way Width: Approximately 60 feet*

    *Exact structure, height and right-of-way requirements may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.