Hemlock - BrysonTransmission Line Project


AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers in Meigs County. The Hemlock-Bryson Transmission Line Project involves building about 4 miles of 69-kilovolt power line, installing switch equipment and upgrading a substation.

Project Updates

Fall 2025: As the project progresses, the project team adjusted the construction schedule to allow for continued discussions with impacted landowners. Property ROW, LLC continues to serve as AEP Ohio's right-of-way-representative for this project.

Map

Project Map (PDF)

Timeline

Open project timeline modal

Structures

Open project structure modal

The project involves the use of single, steel poles.

Structure Height: 60-80 feet*
Right-of-Way Width: 50-60 feet*

*Exact structure, height and right-of-way may vary

Resources

Property Easements Project Fact Sheet Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

AEP Ohio Outreach

614-933-2998
AEPOhio_Outreach@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.