LEGEND

    Yorktown Area Improvements Project

    Indiana Michigan Power (I&M) plans to strengthen the transmission system in eastern Indiana. The improvements in Delaware County would increase reliability, lessen power outages, and speed recovery of service when outages occur.

    Project Updates

    Late Summer 2019: Indiana Michigan Power (I&M) announces the final proposed route for the Yorktown Area Improvements Project.

    Summer 2019: Indiana Michigan Power (I&M) announces the Yorktown Area Improvements project.

    A public Open House will be held to gather input from local residents. Representatives from I&M will be available to discuss specific aspects of the project and to answer questions residents may have. Feedback from the community will be gathered from this event and used to help determine the final proposed line route. The Open House will be informal, and can be attended at any time during the evening and is scheduled for Thursday, June 20 from 5:30 PM-7:30 PM at the Yorktown High School Cafeteria, 1100 South Tiger Drive, Yorktown, IN.

    Project Releases

    Project Map

    Fact Sheet

    Timeline


    Structures

    I&M will build the line with steel monopole structures averaging 75-feet in height. Structures will be placed within a 60-foot right-of-way. I&M is committed to meeting the energy needs of customers while protecting the environment and natural beauty of the region.

    *Exact structure, height and right-of-way may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.