AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers in Van Wert County.
The West Van Wert – Ohio City Transmission Line Rebuild Project involves:
A section of the Project requires regulatory approval by the Ohio Power Siting Board (OPSB).
Plans call for rebuilding the power line in the existing right-of-way, although company representatives might need to acquire new easements or supplement current easements to ensure the safe construction, operation, and maintenance of the line
Summer 2024: Construction for this project is underway and scheduled to be completed in summer 2025.
This project involves the use of steel single-pole structures.
Structure Height: 70-85 feet*
Right-of-Way Width: 60 feet*
*Exact structure, height, and right-of-way requirements may vary.