AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers in Tuscarawas, Guernsey, Coshocton and Muskingum counties.
The Philo-Newcomerstown Area Improvements Project involves:
Company representatives plan to build the power line in an approximate 100 foot wide right-of-way corridor and plan to acquire new easements to ensure the safe construction, operation and maintenance of the line. Company officials plan to construct the project in sequences. Not all sections of the project will be under construction at once.
November 2024: AEP Ohio representatives filed an Application with the Ohio Power Siting Board (OPSB) in October 2023. OPSB representatives have determined the public hearings for this proposed project.
Local Public Hearing - Tuesday, December 10, 2024, at 5:00 p.m.
Adjudicatory Hearing - Tuesday, January 21, 2025, at 10:00 a.m.
AEP Philo-Newcomerstown OPSB Application (PDF)
This project involves the use of steel single-poles.
Structure Height: Approximately 120 feet*
Right-of-Way Width: Approximately 100 feet*
*Exact structure, height and right-of-way requirements may vary.
AEP Ohio provides electricity to nearly 1.5 million customers.
614-933-2998
AEPOhio_Outreach@aep.com
Your message has been sent! We'll be in touch shortly.