AEP Transmission representatives plan power grid upgrades in New Albany in Licking County.
The Kiber 138-kV Transmission Line Project involves:
Adding the new substation and transmission lines allow the company to better distribute electricity throughout the grid, serve an area customer, and meet the area's growing electrical demand.
*Requires Ohio Power Siting Board (OPSB) approval
Fall 2026: Construction was previously scheduled to begin in spring 2026. As the project continues to develop, the project team is reevaluating the construction schedule. An updated timeline will be posted once it is determined.
Spring 2026: The OPSB approved both Letter of Notification applications.
Fall 2025:
AEP Transmission representatives announce the Kiber 138-kV Extension Transmission Line Project. AEP Transmission officials filed the following project components with the Ohio Power Siting Board (OPSB):
This project involves the use of double circuit, steel pole structures.
Structure Height: 120-135 Feet*
Right-of-Way Width: 100 Feet*
*Exact structure, height, and right-of-way requirements may vary.
Ohio Power Company provides electricity to nearly 1.5 million customers.
614-933-2998