Sabine ParishTransmission Improvements Project


SWEPCO officials plan to enhance the local power grid in northwest Louisiana. These enhancements support economic development in the area and ensure continued reliable service for area customers.

The project involves:

  • Building a new substation
  • Building approximately 8 miles of 69-kilovolt transmission line
  • Acquiring 80-foot-wide easements for the new power line
  • Clearing trees and other woody-stemmed vegetation from within the 80-foot right-of-way

 

Timeline

 
Project Timeline
 

Structures

Structure

SWEPCO crews plan to install single-pole steel structures.

Typical Height: 75 feet
Typical Distance Between Structures: 400 feet
Typical Right-of-Way Width: 80 feet


*Exact structure types, height and right-of-way requirements may vary

Typical Substation

Structure

Proposed Substation Footprint: 220 by 200 feet

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

SWEPCO serves 535,000 customers in western Arkansas, northwest and central Louisiana, northeast Texas and the Texas Panhandle.

www.SWEPCO.com

Michael Harris

Project Outreach Specialist
918-231-8047
mhharris@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.