    Leon - Ripley Transmission Rebuild Project

    Appalachian Power and its affiliate, AEP West Virginia Transmission Company, plan to increase the reliability to customers in West Virginia by making upgrades to the existing transmission grid.

    The Leon - Ripley Transmission Rebuild consists of rebuilding about 14 miles of transmission line, expanding the Ripley Substation and making upgrades to the Leon Substation to help reduce the potential of extended outages to customers.

    Construction is expected to start in 2018 and be completed by the end of 2019. Estimated budget for the project is $32 million.


    Project Update

    3/25/2019 - Construction of the Leon - Ripley Transmission Rebuild project is underway. The project is expected to be complete by the end of the year.

    News Releases

    Maps

    Fact Sheets

    Timeline


    Structures


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.