    Dublin West Innovation District Improvements

    AEP Ohio plans to strengthen the electric transmission system in the Dublin West Innovation District.

    The project involves:

    • Building about 3 miles of power line
    • Upgrading two substations
    • This project requires Ohio Power Siting Board (OPSB) approval

    Project Updates

    Late 2019: A public open house took place on September 23, 2019. Company representatives answered questions and gathered input from local residents. Study segments are currently being evaluated.

    Project Releases

    Fact Sheet

    Timeline


    Structures

     

    Company representatives plan to install steel, single-pole structures with an estimated aboveground height of approximately 65 feet, except where taller poles are necessary for distribution underbuild or to meet clearance requirements.

    • Right-of-Way Width: Approximately 80 feet

    *Exact structure, height and right-of-way may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.