North WoosterArea Reinforcements


The need for improvements to the transmission system north of Wooster is essential to ensure an adequate supply of electricity is available for the area's industrial, commercial, and residential customers. Improvements reconfigure the design of the electric system by creating a loop. This loop adds redundancy, reducing power outages in the area and speeding recovery of service when outages occur.

Project components include:

  • Building a new Clutch Switch Substation
  • Constructing just over 2 miles of 69 kilovolt transmission line
  • Constructing a new Schafrath Switch

Project Updates

Early 2020: Phase 1 of the project is complete. Right-of-way agents are working with landowners on Phase 2.

Timeline

Project Timeline

Structures

Structure

AEP Ohio plans to use wood poles approximately 65 to 75-feet tall. Structures will be placed in a 50-foot right-of-way corridor.

* Exact structure, height and right-of-way may vary

Resources

AEP Right-of-Way Process Project Fact Sheet Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

Joe Demaree

Project Outreach Specialist