The Berrien Springs Area Improvements Project involves:

  • Building the Blossom Trail Substation in Eau Claire
  • Building approximately 1/2 miles of transmission line to connect the new Blossom Trail Substation to existing lines
  • Replacing Berrien Springs Substation with the new Boxer Substation in Berrien Springs
  • Rebuilding sections of transmission lines to connect to new structures

Project Updates

Late 2019: I&M announces the Berrien Springs Area Improvement Project

Map

Project Map (PDF)

Timeline

Project Timeline

Structures

Structure

I&M plans on using steel monopole structures averaging 75-feet in height. Structures will be placed within a 60-foot right-of-way.

* Exact structure, height and right-of-way may vary

Resources

Project Fact Sheet Access Roads Field Activities

Indiana Michigan Power serves 575,000 customers in Indiana and Michigan.

www.IndianaMichiganPower.com

Scott Yarbrough

Project Outreach Specialist
260-466-7929
sayarbrough@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.