    Berrien Springs Area Improvements

    The Berrien Springs Area Improvements Project involves:

    • Building the Blossom Trail Substation in Eau Claire
    • Building approximately 1/2 miles of transmission line to connect the new Blossom Trail Substation to existing lines
    • Replacing Berrien Springs Substation with the new Boxer Substation in Berrien Springs
    • Rebuilding sections of transmission lines to connect to new structures

    Project Updates

    Late 2019 - I&M announces the Berrien Springs Area Improvement Project

    Fact Sheet

    Map

    Timeline


    Structures

    I&M plans on using steel monopole structures averaging 75-feet in height. Structures will be placed within a 60-foot right-of-way.

    *Exact structure, height and right-of-way requirements may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.