    Ellerbe Road - Lucas Transmission Line Rebuild Project

    Southwestern Electric Power Company (SWEPCO) plans to invest $9 million to upgrade electric transmission infrastructure near Line Avenue and Ellerbe Road in Shreveport. The project involves replacing aging wooden poles with steel single poles and installing new wire along approximately 3 miles of transmission line in southeast Shreveport. Construction began Fall 2018 and is expected to be complete by Spring 2019.

    Project Updates

    SWEPCO held a come-and-go open house on Tuesday, June 12, 2018, from 5 p.m. to 7 p.m. at the Caddo Middle Magnet School auditorium at 7635 Cornelius Lane in Shreveport.

    Project Releases

    Fact Sheet

    Timeline


    Structures

    Structure A Information:
    • Typical Structure Height: 95 feet
    • Typical Distance between Structures: 350 feet
    • Typical Right-of-Way Width: 100 feet
    Structure B Information:
    • Typical Structure Height: 90 feet
    • Typical Distance between Structures: 450 - 600 feet
    • Typical Right-of-Way Width: 100 feet

    *Exact structure, height and right-of-way may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.