    Roanoke - Marion Transmission Line Rebuild Project

    Indiana Michigan Power (I&M) is rebuilding approximately 37 miles of existing 138-kilovolt (kV) transmission line connecting the Sorenson Substation in Roanoke to the Deer Creek Substation in Marion. The improvements are essential to ensure continued reliable electric service for customers across the region. Double-circuit structures utilizing Breakthrough Overhead Line Design® (BOLD®) will maximize the infrastructure's performance while minimizing environmental impacts and overall system costs.

    Project Updates

    Early 2019: Construction on the Sorenson-Huntington Junction has been completed. Construction on Rock Creek-Van Buren has been completed and crews are working to restore access roads. Huntington Junction-Rock Creek is currently under construction, and is expected to be completed by Late 2019. 

    Fall 2017: Right-of-way agents have begun contacting affected landowners on the first phases of the project, where needed.

    Fact Sheet

    Timeline

     

    PHASE 1: Sorenson - Huntington Junction

    Surveys & Engineering: Spring 2017 - Summer 2017
    Right-of-Way Acquisition: Fall 2017 - Spring 2018
    Construction: Spring 2018 - Summer 2018
    Restoration: Summer 2018 - Late 2018

    PHASE 2: Rock Creek - Van Buren

    Surveys & Engineering: Spring 2017 - Summer 2017
    Right-of-Way Acquisition: Late 2017 - Spring 2018
    Construction: Summer 2018 - Fall 2018
    Restoration: Fall 2018 - Spring 2019

    PHASE 3: Huntington Junction - Rock Creek

    Surveys & Engineering: Spring 2017 - Summer 2017
    Right-of-Way Acquisition: Late 2017 - Spring 2018
    Construction: Fall 2018 - Spring 2019
    Restoration: Spring 2019 - Late 2019

    PHASE 4: Van Buren - Dooville

    Surveys & Engineering: Spring 2017 - Summer 2017
    Right-of-Way Acquisition: Early 2018 - Summer 2018
    Construction: Spring 2019 - Summer 2019
    Restoration: Summer 2019 - Early 2020

    PHASE 5: Dooville - Deer Creek

    Surveys & Engineering: Spring 2017 - Summer 2017
    Right-of-Way Acquisition: Early 2018 - Summer 2018
    Construction: Summer 2019 - Fall 2019
    Restoration: Fall 2019 - Spring 2020

     

    *Project schedule is subject to change.

    Structures

    New structures with the BOLD design will range between 80 and 90 feet in height. They will replace existing structures that are approximately 100 feet in height. Structures will be placed in the existing right-of-way corridor.

    I&M is committed to meeting the energy needs of customers while protecting the environment and natural beauty of the region.

    *Exact structure, height and right-of-way may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.